Best practices in percentage of completion accounting

subtitle
How to reflect the company’s value
date
October 03, 2019
gradient-overlay
green
breadcrumb

Home

Insights

Services

Audit and assurance

  • Audit
  • Professional services
  • Business services

Across the diverse firms that make up the business and professional services (BPS) industry, the percentage of completion (POC) method of accounting is commonly utilized for revenue recognition. Unfortunately, there are many variables affecting the calculation – which in turn can have significant implications to a project’s estimated profitability prior to completion and the valuation of a business during the company sale. Long-term projects can thus pose a particular challenge when accounting for revenue.

This article, the first in a two-part series on POC, will explore accounting best practices. Part two will discuss implications of POC in the context of a business sale.

Background: Cost-to-cost vs. units-of-delivery calculation methods

Under the POC method, revenue is recognized as a function of project price multiplied by the percentage of work completed. There are two general POC calculation methods: cost-to-cost and units-of-delivery.

Cost-to-Cost – Revenue is recognized in relation to actual costs incurred to date relative to total estimated costs. It is based on input costs such as labour hours and machine hours. This method is most accurate if the project accountant regularly reviews and revises the total estimated project cost to ensure the most up-to-date cost information is applied in the recognition of revenue. If cost information is not correct, there is a risk that the appropriate gross profit will not be reflected.

Units-of-Delivery – Revenue is recognized based on the percentage of units produced or delivered to the buyer to the total number of units to be produced or delivered under the terms of the contract with a buyer. This method could lead to changing gross margins over the project as costs are not correlated back to the revenue recognition.

Both methods of POC involve a significant level of estimation of cost to complete a project. Estimates to complete are highly subjective, could be biased, and actual results may differ from estimated results. As the project progresses, updates to estimates may occur. Therefore, they can affect recognized revenue to date and lead to large swings in the period of change. Specifically, the financial results from one period to another may be misleading when the change in estimate causes a higher or lower reported gross profit for a project across accounting periods.

Best practices: Better estimating POC

Below are some best practices to enable management to understand where they are in a project and to be in the best position to estimate the costs required to complete the project:

Benchmarking against previous projects

The hindsight achieved from previous experience can assist in not only developing an initial budget or estimate for a project but also in being able to identify and anticipate roadblocks or delays on a timely basis and incorporate those lessons learned into future estimates. The ability to look back on previously completed projects is only effective if the information relating to those projects is appropriately captured and stored. There are many software programs and systems available that have modules to assist with estimation and project management, which may reduce the likelihood of calculation errors and can represent a central repository for all decision makers to access.

Monthly accountability meetings

Those involved in any long-term projects will agree that an initial estimate can be well-generated and supported; however, there are often surprises and contingencies that pop up along the way that may change those initial assumptions and estimates. Having monthly accountability meetings is key in ensuring that the lines of communication remain open between finance and project management. Such meetings are meant to be a deep dive into the progress and status of the project. While many firms claim to hold such meetings, the key factors that distinguish between an effective and ineffective meeting include (but are not limited to) the following:

In-depth debrief

It is a good practice to debrief the overall project once completed. This serves to assess and validate:

Finally, it is important to document notes from the debrief. Not only will this serve as a learning point for future projects, but it will also enable the company to identify patterns or weaknesses across multiple projects and better understand the root cause of those weaknesses.

Bringing it all together

Overall, POC accounting involves a significant amount of estimation, specifically in establishing the cost to complete, which in turn drives the percentage of completion of a project at a particular point in time. There are many variables that impact this calculation which not only affects the overall profitability of a project, but can have significant implications on the valuation of a business. Using some of the best practices above will assist a company in having better information available to avoid significant swings in project results and provide a more accurate picture of the status and progression of the project.